About the Project

Along Portland & Western's Toledo District, six grade crossings undergo reconstruction and modernization, including five existing vehicle crossings and one new pedestrian crossing near the Oregon State University campus in Corvallis, Oregon.  

Need 

The one-mile section of track runs at walking-speed conditions due to aging crossings, fouled ballast, and deteriorating infrastructure. Six grade crossings needed reconstruction to bring the corridor into a state of good repair, including replacement of fouled ballast, culverts, and track surfacing. Signal modernization addressed outdated crossing protection at 26th Avenue, while the addition of a new signalized crossing at 13th Avenue and a pedestrian crossing improved safety for the surrounding community. 

Work

  • Demolish existing surface and track at each grade crossing 
  • Excavate and replace subballast and AC underlayment 
  • Construct full-depth track and install precast crossing panels 
  • Replace the existing signalized crossing system at 26th Avenue 
  • Install a new signalized crossing at 13th Avenue 
  • Relay standard wood ties across the one-mile section 
  • Remove fouled ballast and restore shoulder 
  • Replace culverts and clean ditches 
  • Line and surface the section of track 

Impact  

The rebuilt crossings and track will give trains a safer, more reliable path through the corridor and provide updated technology to protect drivers, cyclists, and pedestrians at two of its busiest intersections.   

Quick Facts

Location

Corvallis, OR

Project Type

Specialty Rail

Delivery Method

Bid-Build

Date Completed

2026

Project Owner

Portland & Western Railroad

Region

Northwest